A pressure plug is a stabilization job involving piping and container systems designed to stop leaks and protect the stability of workers. Below, I will detail the correct method of plugging with pressure and provide some advice and considerations.
1. Preparation:
A stability assessment must be carried out and the workplace must be safe before a pressure plug can be carried out.
- Check the integrity and suitability of all related equipment and tools.
- Ensure that staff are trained and aware of safety procedures and emergency measures.
2. Determine the plugging point:
- Determine the location of the pipe or container system with pressure seal, as required.
- Determine the force and temperature before and after the plugging point, and understand the relevant materials and media.
3. Choose the right plugging appliance:
- According to the characteristics of the pipeline or container system, select the appropriate plugging equipment such as plugging ball, plugging plate, etc.
- Ensure that the material and dimensions of the plug are correct and can withstand the required pressure and temperature.
4. Preparations for plugging:
- Clean the area around the sealing point to ensure that there is no debris and dirt.
- Using the appropriate tools, check the integrity and tightness of the plug appliance.
- Apply appropriate sealants or lubricants as needed to ensure tight connection of the sealer piping or container system.
5. Perform plugging:
- Gently place the plug appliance to the plug point and ensure that the plug area is properly inserted or covered.
- Gradually increase the pressure and observe the reaction and effect of the plugging device.
- Before increasing the pressure, use tools such as pressure gauges to monitor the pressure and ensure that the pressure does not exceed the capacity of the plug.
6. Monitoring and maintaining closure:
- Continuously monitor the pressure and temperature after plugging and ensure the stability and tightness of the plugging apparatus.
- Periodically check the status of the plug appliance, especially in the case of prolonged operation or exposure to harsh environments.
7. Unplugging:
- When unplugging is required, caution must be exercised to avoid accidental leakage and injury.
- Gradually reduce the pressure while using appropriate tools and equipment to remove the plug from the plug point.
- After unplugging, perform necessary cleaning and maintenance work and ensure the normal operation of the pipeline or container system.
8. Record and report:
- Record relevant data and observations, including force, temperature, use of the plug apparatus, etc., during the process of sealing with pressure.
- After the completion of the work, report the results of the work and any anomalies found in a timely manner.
When performing pressure plugging, the following points should also be noted:
- Operate strictly in accordance with relevant stability standards and procedures.
- Use appropriate personal protective equipment such as gloves, goggles and respirators.
- Maintain clear communication and close contact with team members during the closure process.
- Prepare for emergencies and be familiar with emergency procedures.
- Regular training and exercises are conducted to ensure the operational skills and emergency response capability of staff.
In summary, pressure plugging involves complex engineering and stability issues that must be handled with care and in accordance with relevant procedures and procedures. The stability and effectiveness of the work can be ensured through proper preparation, selection of the appropriate plug equipment, and continuous monitoring and maintenance of the stability of the plug.
Get more knowledge about What to Look for When Choosing an hot tapping machine Manufacturer please refer to aoguang sandwich valve:https://www.pipelinehottapping.com
Prev:Construction principle with pressure sealing
Next:What is the difference between plugging with pressure and plugging without pressure?